Climate Change Data Portal
DOI | 10.16285/j.rsm.2023.0545 |
Present in situ stress measurement in the eastern segment of Yarlung Zangbo River fault and fault activity analysis | |
Sun Wei-feng; Huang Huo-lin; Sun Dong-sheng; Meng Wen; Chen Qun-ce | |
发表日期 | 2024 |
ISSN | 1000-7598 |
起始页码 | 45 |
结束页码 | 4 |
卷号 | 45期号:4 |
英文摘要 | In order to determine the in situ stress state of the newly built hydropower station project in Jiacha county, and understand the activity of the eastern segment of the Yarlung Zangbo River fault zone, we obtained the in situ stress data in the engineering field by using the self-developed deep-hole stress measuring equipment based on the hydraulic fracturing method. We analyzed the fault activity by employing the Mohr-Coulomb failure criterion and the collected in situ stress data along the eastern segment of the Yarlung Zangbo River fault zone. The results showed that: (1) The magnitudes of the maximum horizontal stress SH ranged from 6.07 MPa to 37.62 MPa, the values of the minimum horizontal stress Sh were from 3.13 MPa to 20.33 MPa at the depth from 122.75 m to 418.75 m, and the dominant direction of the measured maximum horizontal principal stress was nearly NNE. (2) The stress regime was mainly characterized by SH> Sh> Sv (Sv is the vertical principal stress), which was prone to reverse faulting. (3) Most of the measured and collected Mohr stress circles intersected the failure threshold line with friction coefficient equal to 0.6, which indicated that the eastern segment of the Yarlung Zangbo River fault zone was in a high level of fault slip instability. Furthermore, the fault slip risk of the west section from Gongga to Langxian was higher than that of the east section near Linzhi along the eastern segment of the Yarlung Zangbo River fault zone. |
英文关键词 | in situ stress; hydraulic fracturing method; fault activity; Yarlung Zangbo River fault; Qinghai-Tibet plateau |
语种 | 英语 |
WOS研究方向 | Engineering |
WOS类目 | Engineering, Geological |
WOS记录号 | WOS:001223065500017 |
来源期刊 | ROCK AND SOIL MECHANICS
![]() |
文献类型 | 期刊论文 |
条目标识符 | http://gcip.llas.ac.cn/handle/2XKMVOVA/288933 |
作者单位 | China Geological Survey; Chinese Academy of Geological Sciences; Institute of Geomechanics, Chinese Academy of Geological Sciences; Ministry of Natural Resources of the People's Republic of China; POWERCHINA Huadong Engineering Corporation Limited |
推荐引用方式 GB/T 7714 | Sun Wei-feng,Huang Huo-lin,Sun Dong-sheng,et al. Present in situ stress measurement in the eastern segment of Yarlung Zangbo River fault and fault activity analysis[J],2024,45(4). |
APA | Sun Wei-feng,Huang Huo-lin,Sun Dong-sheng,Meng Wen,&Chen Qun-ce.(2024).Present in situ stress measurement in the eastern segment of Yarlung Zangbo River fault and fault activity analysis.ROCK AND SOIL MECHANICS,45(4). |
MLA | Sun Wei-feng,et al."Present in situ stress measurement in the eastern segment of Yarlung Zangbo River fault and fault activity analysis".ROCK AND SOIL MECHANICS 45.4(2024). |
条目包含的文件 | 条目无相关文件。 |
除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。