Exploring the link between project delays and cancelation rates in the U.S. rooftop solar industry
Cook J.J.; Cruce J.; O'Shaughnessy E.; Ardani K.; Margolis R.
发表日期2021
ISSN03014215
卷号156
英文摘要About 1 in 10 rooftop solar photovoltaic (PV) customers who sign a contract to install a PV system cancel their contract before the system is installed. Although some cancelation risk is inherent in the solar industry, there may be ways to reduce cancelation volume, such as reducing project delays. Delays can occur at each stage of PV adoption processes, which take several weeks to months from contract signature to system operation. Using data from a recent survey of PV installers, we explore the factors that explain PV project delays and cancelations. The survey data suggest that PV adoptions take about 16 weeks, on average, from contract signature until system operation. Survey respondents consistently identified permitting, inspection, and interconnection (PII) processes as key drivers of project delays. Most respondents then suggested these PII-related delays increase contract cancelations. However, larger-scale installers report higher cancelation rates, and these installers rank changes in customer financial situations higher than PII-related delays as the main cause for cancelations. Most respondents also reported avoiding jurisdictions with particularly onerous PII requirements or charging more in these jurisdictions. On balance, the results provide a rationale for measures to streamline PII processes to reduce delays and potentially mitigate cancelation risk. © 2021 Elsevier Ltd
关键词CancellationsInspectionInterconnectionPermittingSolarUtilities
英文关键词Risk assessment; Solar power generation; Surveys; Cancelation; Contract signature; Interconnection; Permitting; Photovoltaics; Project delays; Solar; Solar industries; Systems operation; Utility; Inspection
语种英语
来源期刊Energy Policy
文献类型期刊论文
条目标识符http://gcip.llas.ac.cn/handle/2XKMVOVA/205062
作者单位National Renewable Energy Laboratory, 15013 Denver West Parkway, GoldenCO 80401, United States; Clean Kilowatts, LLC, United States
推荐引用方式
GB/T 7714
Cook J.J.,Cruce J.,O'Shaughnessy E.,et al. Exploring the link between project delays and cancelation rates in the U.S. rooftop solar industry[J],2021,156.
APA Cook J.J.,Cruce J.,O'Shaughnessy E.,Ardani K.,&Margolis R..(2021).Exploring the link between project delays and cancelation rates in the U.S. rooftop solar industry.Energy Policy,156.
MLA Cook J.J.,et al."Exploring the link between project delays and cancelation rates in the U.S. rooftop solar industry".Energy Policy 156(2021).
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Cook J.J.]的文章
[Cruce J.]的文章
[O'Shaughnessy E.]的文章
百度学术
百度学术中相似的文章
[Cook J.J.]的文章
[Cruce J.]的文章
[O'Shaughnessy E.]的文章
必应学术
必应学术中相似的文章
[Cook J.J.]的文章
[Cruce J.]的文章
[O'Shaughnessy E.]的文章
相关权益政策
暂无数据
收藏/分享

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。